Engineering Switch Upgrade
Program Continues
Ongoing. Still have a couple of old Cisco switches to upgrade
across
Engineering.
DHCP project
A number of departments within Engineering are still hard
coding IP
numbers. A project has been put forward to migrate these groups to use
DHCP. This will require physically or remotely visiting each affected
machine. Timeline for completion, end of 2009.
Aruba switchover project
DWE, EC office area and CBET still need to be done.
DC Point Of Presence project
The 16 Engineering switches in DC are being moved to direct fibre
connections to a new POP in the building located in the CIM part of DC
with a link back to the Engineering router. The last remaining Extreme
switches in DC are being replaced at the same time. The work is about
80% done. There are a few switches left to upgrade.The long
term plan is to, as part of the DHCP project, renumber the machines and
turn on some routing for the building.