Engineering Systems Administrator Group
Minutes April 12, 2001
prepared by Erick Engelke
Present:
-
Chair: Martin MacLeod, Engineering Computing
-
Erick Engelke, Engineering Computing
-
Hon Tam, Engineering Computing
-
Dave Walsh, Engineering Computing
-
Mahindra Sangara, Systems Design
-
Richard Scott, Civil Engineering
-
Dennis Herman, Chemical Engineering
-
Steve Hitchman, Mechanical Engineering
-
Ray White, IST
-
Hector Budman, Associate Dean for Computing, Faculty of Engineering
-
Mike Herz, Civil Engineering
Regrets
-
Paul Martin, Management Sciences
-
Bernie Roehl, Electrical and Computer Engineering
-
Eric Praetzel, Electrical and Computer Engineering
Discussion
1. Netapp
2. Davis Centre Switches and Cabling
-
Several departments have a Davis Centre presense
-
Erick has allocated passwords for departmental reps on Extreme switches
and is currently in the process of getting keys for the various rooms
3. Web Links
4. Nexus Name
-
APC has approved the name: Nexus
-
Hon explained the empty root for schema, DNS, GC for better reliability
and flexibility
-
test domain will be in different forest to test schema changes
-
no plans for another peer domain, but it is possible
-
Hector said APC aware we will move many machines to W2K, but timing is
undetermined
-
Bruce suggested conversion to be completed by September 2002, but this
assumes hardware upgrades can be budgetted and implemented
-
Mike asked if there will be any problems if, say, Civil doesn't join Nexus
for staff and faculty. EC doesn't envision any major problems, but
did mention several reasons. Mike was not swayed by these suggestions.
5. Third Year CFI
-
$ 175 per drop estimate includes parts and labour
-
better keep very good records if costs are more than average - eg. asbestos,
long runs
-
cannot claim $175 for easy runs and more for hard runs, whichever is higher
-
must keep records of the time spent
-
$135k is left for Engineering for the 3rd year
-
Martin will get an updated spreadsheet
-
switch priceses have fallen - uncertain how much money this will free up
for the 3rd year
-
Dennis wonderred if 2nd year work can be filed still, Hector will look
into this case. First estimate approximately $10k, but then Steve
points out that Chemical budgetted only $6k, and Martin observed that Chemical
was billing $175 + parts. Dennis will re-visit these costs.
6. Cabling Procedures in Engineering
Most of discussion focused on the predocumentation
issue
-
Mike: predoc is unnecessary and wasteful of time. In his construction
experience, detailed pre-built wiring drawings for these types of wires
are never done. Usually only textual wire data and sometimes schematics.
-
Mike hesitant to do predoc when installing departmental room wiring, but
understands when doing public hallways
-
Dave: if you want CFI you basically have to predoc
-
Hector: this is not only a CFI issue, it is a requirement for all wiring
-
Several people pointed out that plant ops and IST would prefer if we didn't
wire at all, we had to struggle to be allowed to wire, predoc is one of
the concessions we have to make to retain this right
-
Mike: this creates 3 layers of beauocracy, it's too much
-
Dennis agreed
-
Mike: EC knows all the parts we buy
-
Dennis: we buy all hardware from same source
-
Bruce: points to section 1.5, #4 in the
guidelines , we are bound to follow it
-
Hector: it's not approval, it is a sharing of information
-
Dennis: 90% of time we don't need special shared information
-
Bruce: who convinces plant ops that we need to change rules
-
Mike: can't we make some sort of compromise. We already provide details
during IP requests, why not add a few more details. Also, IST's requirement
for predocs is void of any details, this means anything we provide could
be considerred adequate.
-
Bruce drew a simple diagram and showed the bare essentials of what is required
-
Mike: can't we just draw two boxes and a line connecting them
-
Martin gaven an example of why a straight line is insufficient - wiring
must follow the contours of the wall
-
Mike: don't always know everything in advance, like heating ducts, until
ceiling is open, should draw the diagram afterwards, happy to do it then
-
Mike wants a detailed checklist of all the steps to be taken before and
after laying a wire, current document is too vague
-
Martin: current document allows room for flexibility and user judgement
-
Erick: need predoc, otherwise everything is already laid and thus grandfatherred
discussion halted due to time constraints