Engineering Switch Replacement Program Continues
Ongoing. All switches have been re-distributed to the various Engineering departments and are being installed.
Engineering additions/renovations
A number of additions/renovations are being completed in Engineering that require major wiring/rewiring
Mansci third floor addition above Multi Media lab, 200 drops, finished
Mansci fourth floor lab and conference room 76 drops, finished
Old IRR area made into offices, 42 drops, half finished
Minor renovation DWE-2532 16 drops, finished
Major renovation DWE second floor office area, 174 drops + one TR, finished