Engineering Switch Replacement Program Continues 

Ongoing. All switches have been re-distributed to the various Engineering departments and are being installed.


Engineering additions/renovations


A number of additions/renovations are being completed in Engineering that require major wiring/rewiring

        Mansci third floor addition above Multi Media lab,  200 drops, finished

        Mansci fourth floor lab and conference room 76 drops, finished

        Old IRR area made into offices,  42 drops, half finished

        Minor renovation DWE-2532  16 drops, finished

        Major renovation DWE second floor office area,  174 drops + one TR, finished