skip navigation

 

Engineering Machine room move

 

Engineering Computing is moving it's servers from PHY to a new server room in E5. Racks are in and fibre layed. Fibre just needs to be terminated and switch installed.



DHCP conversion and IP cleanup

 

Ongoing. Most of EIT has been converted to using DHCP. Mechanical Engineering has started moving their clients.

 


Engineering 10 Gig Fibre Upgrades

 

Ongoing. Planning to connect our main backup server to the network at 10 Gigs to reduce "full backups" and a few other critical servers.