Major System Maintenance Procedures

Scope

These procedures apply to operating system upgrades, memory upgrades, disk replacement, and other hardware replacements etc. on major systems such as the Network Appliance file server, e-mail server, web server, network switches connecting such servers, and network switches/routers which provide service to a large user or computer base.

Scheduling the work

The preferred time for major system maintenance operations is Tuesday to Thursday morning, with the work scheduled to complete before 7:30am. For work performed from offsite, it should be scheduled to complete before 7:00am to allow travel time to come onsite if problems arise.

Before performing the work

After performing the work